INSTALLATION
Removal / installation · Vehicles built from Jan 2012
| 1.
INSTALL PCV VALVE SUB-ASSEMBLY |
 |
- Apply a light coat of engine oil to the O-ring.
Text in Illustration
*1
|
O-ring
|
- HINT:
- When reusing the PCV valve, inspect the O-ring.
- If the O-ring has scratches or cuts, replace the PCV valve.
Using a 22 mm ball joint lock nut wrench, install the PCV valve sub-assembly.
-
Torque:
- 3.5 N*m{
36 kgf*cm
, 31 in.*lbf
}
- NOTICE:
- Use the formula to calculate special torque values for situations where a ball joint lock nut wrench is combined with a torque wrench (Click here).
| 2.
INSTALL PCV HOSE |
 |
- Connect the PCV valve hose to the valve.
Secure the hose with the clamp.
Text in Illustration
*a
|
Upper Side
|
*b
|
5 to 10 mm (0.197 to 0.394 in.)
|
- HINT:
- Make sure the direction of the hose clamp is as shown in the illustration.
| 3.
INSTALL NO. 3 ENGINE COVER |
 |
- Install the No. 3 engine cover.
Text in Illustration
 
|
Engine Front
|
- HINT:
- Position the No. 3 engine cover so that the arrow mark faces the front of the engine and install it.
| 4.
INSTALL NO. 4 ENGINE COVER |
 |
- Install the No. 4 engine cover.
Text in Illustration
 
|
Engine Front
|
- HINT:
- Position the No. 4 engine cover so that the arrow mark faces the front of the engine and install it.
| 5.
INSTALL INTAKE MANIFOLD |
 |
(Click here)