Use the same procedure for the RH side and LH side.
The following procedure is for the LH side.
63436B
1.INSTALL NO. 1 ROOF CARRIER SEAL
When installing the No. 1 roof carrier seal, heat the roof rack assembly using a heat light.
| Item | Temperature |
|---|---|
| Roof Rack Assembly | 20 to 30°C (68 to 86°F) |
| *a | Heated Part |
| *b | Heat Light |
Do not touch the heat light and heated parts, touching the heat light may result in burns.
Touching heated parts for a long time may result in burns.
Do not heat the roof rack assembly excessively.
Clean the roof rack assembly surface.
Using a heat light, heat the roof rack assembly surface.
Remove any remaining double-sided tape from the roof rack assembly.
Wipe off any tape adhesive residue with cleaner.
Using a brush or felt, apply primer or equivalent to the No. 1 roof carrier seal installation area.
Use a clean brush or felt.
Do not touch the roof rack assembly until the primer has dried.
Remove the release paper from a new No. 1 roof carrier seal.
After removing the release paper, keep the exposed adhesive free from foreign matter.
Install the No. 1 roof carrier seal as shown in the illustration.
|
Double-sided Tape | - | - |
Press the No. 1 roof carrier seal firmly to install it.
63470B
2.INSTALL ROOF RACK ASSEMBLY
Install the 5 new clips to the roof rack assembly.
Engage the 5 clips.
Install the 2 screws.
Install the roof rack assembly with the bolt.
75632F
3.INSTALL NO. 2 ROOF TOP GARNISH
Engage the guide and claw to install the No. 2 roof top garnish.
75631R
4.INSTALL NO. 1 ROOF TOP GARNISH
Engage the guide and claw to install the No. 1 roof top garnish.
Use the same procedure for the other No. 1 roof top garnish.