Home › ENGINE ยท 2UZ-FE › EMISSION CONTROL › AIR SWITCHING VALVE (for Bank 1)

AIR SWITCHING VALVE (for Bank 1) > INSTALLATION

for Preparation Click here



1. INSTALL AIR SWITCHING VALVE ASSEMBLY


A191536E01
  1. Install the air switching valve with the 3 nuts.

    Torque:
    16 N*m{ 163 kgf*cm , 12 ft.*lbf }

    NOTICE:
    Do not hold the bracket of the air switching valve.



2. INSTALL NO. 3 AIR TUBE


A153518
  1. Temporarily install a new gasket and the No. 3 air tube to the exhaust manifold side with the 2 nuts.

  1. Install a new gasket and the No. 3 air tube to the air switching valve side with the 2 nuts.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }

  1. Tighten the 2 nuts on the exhaust manifold side.

    Torque:
    10 N*m{ 102 kgf*cm , 7 ft.*lbf }



3. INSTALL NO. 2 AIR HOSE


    A153516
  1. Install the No. 2 air hose.



    A191535
  1. Connect the air pump connector.

  1. Connect the fuel hose clamp.



4. INSTALL FRONT FENDER APRON SEAL LH


    A159336
  1. Install the fender apron seal with the 5 clips.



5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
Some systems need to be initialized after the cable is reconnected (Click here).