| *1 | POWER DISTRIBUTION BOX ASSEMBLY | - | - |
|
N*m (kgf*cm, ft.*lbf): Specified torque | - | - |
1. PRECAUTION
|
|
89221
2.INSTALL MAIN BODY ECU (MULTIPLEX NETWORK BODY ECU)
|
|
| *1 | Power Distribution Box Assembly | *2 | Main Body ECU (Multiplex Network Body ECU) |
| *a | 20° or more | *b | Housing Sidewall |
| *c | Side A | *d | Center of Rotation (Contacts Surface A) |
|
Push Area |
|
Set |
|
Slide |
|
Install in this Direction |
|
Rotate in this Direction | - | - |
Set the main body ECU (multiplex network body ECU) to the position where the guide of the main body ECU (multiplex network body ECU) contacts the housing sidewall of the power distribution box assembly as shown in the illustration.
Make sure to keep the angle at 20° or more as shown in the illustration.
Slide the main body ECU (multiplex network body ECU) along the housing sidewall as shown in the illustration and engage the guides.
While keeping the main body ECU (multiplex network body ECU) in contact with side A of the power distribution box assembly (axis of rotation), lower it as shown in the illustration.
Do not strike or apply excessive force to the side surface of the main body ECU (multiplex network body ECU).
While pressing the main body ECU (multiplex network body ECU) against side A (center of rotation) of the power distribution box assembly, rotate it until it enters the lock of the power distribution box assembly.
Press the push area until the claw engages to install the main body ECU (multiplex network body ECU).
Make sure to press only the push area.
Confirm the engagement of the main body ECU (multiplex network body ECU) and power distribution box assembly by listening for the click sound of the lock engaging.
If a click sound cannot be heard, visually check the engagement of the lock. The engagement can also be confirmed if the main body ECU (multiplex network body ECU) and power distribution box assembly are flush.
82715
3.INSTALL WIRING HARNESS CLAMP BRACKET
Engage the guides to install the wiring harness clamp bracket to the power distribution box assembly with multiplex network body ECU.
Temporarily install the bolt.
4.INSTALL POWER DISTRIBUTION BOX ASSEMBLY WITH MULTIPLEX NETWORK BODY ECU
| *a | Lock Lever | - | - |
Connect the connector.
Connect the 2 connectors and pull down the lock levers to engage the claws and lock the 2 connectors as shown in the illustration.
Engage the claws.
Engage the claws.
Install the power distribution box assembly with multiplex network body ECU with the bolt and 2 nuts.
| *A | for HV Model | - | - |
| *a | Lock Lever | - | - |
Connect the 5 connectors.
for HV Model:
Connect the 2 connectors and pull down the lock levers to engage the claws and lock the 2 connectors as shown in the illustration.
Connect the 2 connectors and pull down the lock levers to engage the claws and lock the 2 connectors as shown in the illustration.
Engage the clamp.
Engage the clamp.
Connect the 5 connectors.
55308B
5.INSTALL NO. 3 INSTRUMENT PANEL TO COWL BRACE SUB-ASSEMBLY
| *a | Bolt (A) | *b | Bolt (B) |
Install the No. 3 instrument panel to cowl brace sub-assembly with the 2 bolts and nut.
55480D
6.INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY
7.CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
for M15A-FKS
Click hereGeneral>MAINTENANCE>M15A-FKS AUXILIARY BATTERY>INSTALLATION
for M15A-FXE
Click hereGeneral>MAINTENANCE>M15A-FXE AUXILIARY BATTERY>INSTALLATION
8. INITIALIZATION AFTER RECONNECTING BATTERY TERMINAL
Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>WORK PROCEDURE
When disconnecting and reconnecting the auxiliary battery, there is an automatic learning function that completes learning when the respective system is used.
Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>AUTOMATIC LEARNING CHART