Home › Drivetrain › DRIVE SHAFT / PROPELLER SHAFT › PROPELLER SHAFT ASSEMBLY › from 2020.09
RM36W0E _52 Drivetrain _087547 DRIVE SHAFT / PROPELLER SHAFT _0448000 PROPELLER SHAFT ASSEMBLY A

DRIVE SHAFT / PROPELLER SHAFT  PROPELLER SHAFT ASSEMBLY  REMOVAL  


CAUTION / NOTICE / HINT

The necessary procedures (adjustment, calibration, initialization, or registration) that must be performed after parts are removed and installed, or replaced during the propeller shaft with center bearing assembly removal/installation are shown below.

Necessary Procedures After Parts Removed/Installed/Replaced
Replaced Part or Performed Procedure Necessary Procedure Effect/Inoperative Function when Necessary Procedure not Performed Link
Gas leak from exhaust system is repaired Inspection After Repair
·

Poor idle, etc.

·

Engine start function, etc.


(Click here)

PROCEDURE

Hide 17410 1.REMOVE FRONT EXHAUST PIPE ASSEMBLY

Hide 58166A 2.REMOVE FRONT FLOOR COVER LH

a.
C448018

Remove the bolt and 3 clips.


b.

Disengage the 6 clamps to remove the front floor cover LH from the vehicle body.


Hide 58165C 3.REMOVE FRONT FLOOR COVER RH

HINT:

Use the same procedure as for the LH side.


Hide 58041A 4.REMOVE FRONT NO. 1 FLOOR HEAT INSULATOR SUB-ASSEMBLY

a.
C451195

Remove the 2 nuts and front No. 1 floor heat insulator sub-assembly from the vehicle body.


Hide 37100 5.REMOVE PROPELLER SHAFT WITH CENTER BEARING ASSEMBLY

a.
C451196

Remove the 2 bolts and 2 center No. 2 support bearing washers, and separate the center support bearing.


b.
C451197C01
1.688,1.698 2.177,1.938 2.177,1.938 1.719,1.563 true 2.208,1.875 2.448,2.083 0.24,0.208 10 true *a
*a Matchmark


Place matchmarks on the rear differential carrier assembly and propeller shaft with center bearing assembly.


c.

Remove the 4 nuts and 4 washers, and separate the propeller shaft with center bearing assembly from the rear differential carrier assembly.


d.
C451198C01
1.729,1.583 2.177,1.844 2.177,1.844 1.76,1.427 true 2.219,1.771 2.469,1.979 0.25,0.208 10 true *a
*a Matchmark


Place matchmarks on the transfer assembly and propeller shaft with center bearing assembly.


e.

Remove the 4 nuts and 4 washers, and separate the propeller shaft with center bearing assembly from the transfer assembly.