Use the same procedure for RHD and LHD vehicles.
The procedure listed below is for LHD vehicles.
84152
1.INSTALL HEADLIGHT LEVELING SWITCH
Engage the claws to install the headlight leveling switch.
55480D
2.INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY
53601
3.CONNECT HOOD LOCK CONTROL LEVER SUB-ASSEMBLY
55317E
4.INSTALL NO. 1 INSTRUMENT SIDE PANEL
62312B
5.CONNECT FRONT DOOR OPENING TRIM WEATHERSTRIP LH
55606
6.INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY
62112
7.INSTALL COWL SIDE TRIM BOARD LH
67914B
8.INSTALL FRONT DOOR SCUFF PLATE LH
58802E
9.INSTALL FRONT CONSOLE BOX SUB-ASSEMBLY (for 5 Door)
58810J
10.INSTALL CONSOLE BOX ASSEMBLY (for 3 Door)
33554
11.INSTALL SHIFT LEVER CAP (for CVT)
33504F
12.INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY (for Manual Transmission)
33504F
13.INSTALL SHIFT LEVER KNOB SUB-ASSEMBLY (for CVT)
for TMC Made:
Click hereDrivetrain>K320 (MULTIDRIVE / CVT)>SHIFT LEVER KNOB (for TMC Made)>INSTALLATION
for TMMF, TMMCZ Made:
Click hereDrivetrain>K320 (MULTIDRIVE / CVT)>SHIFT LEVER KNOB (for TMMF Made)>INSTALLATION
55407B
14.INSTALL SWITCH HOLE BASE SUB-ASSEMBLY
55432B
15.INSTALL LOWER INSTRUMENT PANEL FINISH PANEL
55479D
16.INSTALL LOWER INSTRUMENT CLUSTER FINISH PANEL GARNISH