The necessary procedures (adjustment, calibration, initialization, or registration) that must be performed after parts are removed, installed, or replaced during the combination meter removal/installation are shown below.
*1: When performing learning using the GTS.
*2: w/ Stop and start system
Use the same procedure for RHD and LHD vehicles.
The following procedure is for LHD vehicles.
1. PRECAUTION
After turning the ignition switch off, waiting time may be required before disconnecting the cable from the negative (-) battery terminal. Therefore, make sure to read the disconnecting the cable from the negative (-) battery terminal notices before proceeding with work.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>PRECAUTION
2.DISCONNECT CABLE FROM NEGATIVE BATTERY TERMINAL
for 8NR-FTS:
for 3ZR-FAE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION
55404D
3.REMOVE INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
55470
4.REMOVE INSTRUMENT CLUSTER FINISH PANEL GARNISH ASSEMBLY
55410C
5.REMOVE INSTRUMENT CLUSTER FINISH PANEL ASSEMBLY
55012A
6.REMOVE NO. 2 INSTRUMENT PANEL GARNISH SUB-ASSEMBLY
55414C
7.REMOVE STARTER SWITCH BEZEL (for RHD with Entry and Start System)
83100
8.REMOVE COMBINATION METER ASSEMBLY
Remove the 2 screws.
Disengage the clips and guides.
Disconnect the 2 connectors to remove the combination meter assembly.