Home › Power Source / Network ยท 1AZ-FE BATTERY / CHARGING › GENERATOR

GENERATOR > INSTALLATION

for Preparation Click here



1. INSTALL GENERATOR ASSEMBLY


    A192601E01
  1. Install the generator assembly with the 2 bolts.

    Torque:
    Bolt A:
    52 N*m{ 530 kgf*cm , 38 ft.*lbf }
    Bolt B:
    21 N*m{ 214 kgf*cm , 15 ft.*lbf }

  1. Install the wire harness clamp bracket with the bolt.

    Torque:
    8.0 N*m{ 82 kgf*cm , 71 in.*lbf }

  1. Install the generator wire to terminal B with the nut.

    Torque:
    9.8 N*m{ 100 kgf*cm , 87 in.*lbf }

  1. Install the terminal cap.

  1. Connect the connector and wire harness clamp.