Home › Power Source / Network ยท 2GR-FE BATTERY / CHARGING › GENERATOR

GENERATOR > INSTALLATION

for Preparation Click here



1. INSTALL GENERATOR ASSEMBLY
  1. Install the generator assembly with the 2 bolts.

    Torque:
    43 N*m{ 438 kgf*cm , 32 ft.*lbf }

  1. Connect the wire harness clamp.

  1. Install the generator bracket with the 2 bolts.

    Torque:
    20 N*m{ 204 kgf*cm , 15 ft.*lbf }

  1. Connect the generator connector to the generator assembly.

  1. Install the generator wire with the bolt.

    Torque:
    8.4 N*m{ 86 kgf*cm , 74 in.*lbf }

  1. Install the nut and connect the wire harness to terminal B.

    Torque:
    9.8 N*m{ 100 kgf*cm , 87 in.*lbf }

  1. Install the terminal cap.



2. INSTALL V-RIBBED BELT
(Click here).


3. INSTALL RADIATOR ASSEMBLY
(Click here).


4. INSTALL V-BANK COVER SUB-ASSEMBLY
  1. Fit the 3 retainers and install the V-bank cover sub-assembly.



5. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).