Home › Engine / Hybrid System › 2GR-FE STARTING › STARTER
RM2030EQ _51 Engine / Hybrid System _014641 2GR-FE STARTING _0074455 STARTER A

2GR-FE STARTING  STARTER  INSTALLATION  


PROCEDURE

Hide 28100 1.INSTALL STARTER ASSEMBLY

a.

Install the starter with the 2 bolts.

Torque:
37 N*m (377 kgf*cm, 27 ft.*lbf)


b.

Connect the starter connector.


c.

Install the terminal nut and cover the nut with the cap.

Torque:
9.8 N*m (100 kgf*cm, 87 in.*lbf)


Hide 17701 2.INSTALL AIR CLEANER CASE SUB-ASSEMBLY

Hide 17801 3.INSTALL AIR CLEANER FILTER ELEMENT SUB-ASSEMBLY

Hide 17735 4.INSTALL AIR CLEANER CAP SUB-ASSEMBLY

Hide 17751 5.INSTALL INLET NO. 1 AIR CLEANER

Hide 17752 7.INSTALL INLET NO. 2 AIR CLEANER

Hide 11209 8.INSTALL V-BANK COVER SUB-ASSEMBLY

Hide 9.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable from the negative (-) battery terminal, some systems need to be initialized after the cable is reconnected.

Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION


Hide 53295E 10.INSTALL COOL AIR INTAKE DUCT SEAL