Home › Power Source / Network › 2GR-FE BATTERY / CHARGING › GENERATOR
RM2030EQ _57 Power Source / Network _014661 2GR-FE BATTERY / CHARGING _0074570 GENERATOR A

2GR-FE BATTERY / CHARGING  GENERATOR  INSTALLATION  


PROCEDURE

Hide 27020 1.INSTALL GENERATOR ASSEMBLY

a.

Install the generator assembly with the 2 bolts.

Torque:
43 N*m (438 kgf*cm, 32 ft.*lbf)


b.

Connect the wire harness clamp to the generator bracket.


c.

Install the generator bracket with the 2 bolts.

Torque:
20 N*m (204 kgf*cm, 15 ft.*lbf)


d.

Connect the generator connector to the generator assembly.


e.

Install the wire harness clamp with the bolt.

Torque:
8.0 N*m (82 kgf*cm, 71 in.*lbf)


f.

Connect the wire harness to terminal B with the nut.

Torque:
9.8 N*m (100 kgf*cm, 87 in.*lbf)


g.

Install the terminal cap.


Hide 16400 3.INSTALL RADIATOR ASSEMBLY

Hide 11209 4.INSTALL V-BANK COVER SUB-ASSEMBLY

Hide 5.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION