Home › Power Source / Network › 2GR-FKS BATTERY / CHARGING › GENERATOR › from 2018.09
RM3160E _57 Power Source / Network _060166 2GR-FKS BATTERY / CHARGING _0303645 GENERATOR A

2GR-FKS BATTERY / CHARGING  GENERATOR  INSTALLATION  


PROCEDURE

Hide 27020 1.INSTALL GENERATOR ASSEMBLY

a.

Install the wire harness clamp bracket with the bolt.

Torque:
12.5 N*m (127 kgf*cm, 9 ft.*lbf)


b.

Type A:

i.

Install the generator assembly with the 2 bolts.

Torque:
43 N*m (438 kgf*cm, 32 ft.*lbf)


ii.

Temporarily install the generator assembly bracket with the 2 bolts.


iii.

Fully tighten the 2 bolts.

Torque:
20 N*m (204 kgf*cm, 15 ft.*lbf)



c.

Type B:

i.
A396288

Install the generator assembly bracket to the generator assembly with the bolt.

Torque:
20 N*m (204 kgf*cm, 15 ft.*lbf)


ii.

Install the generator assembly with the 2 bolts.

Torque:
43 N*m (438 kgf*cm, 32 ft.*lbf)


iii.

Install the nut.

Torque:
20 N*m (204 kgf*cm, 15 ft.*lbf)



d.

Engage the 2 wire harness clamps.


e.

Connect the magnetic clutch connector.


f.

Connect the generator assembly connector.


g.

Connect the wire harness to terminal B with the nut.

Torque:
12 N*m (122 kgf*cm, 9 ft.*lbf)


h.

Close the terminal cap.


Hide 4.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION