2014 Hilux · Service Manual TRANSMISSION

INSTALLATION

Removal / installation · Vehicles built Aug 2012 – Jul 2013

Versions by build date: Jun 2011 – Jul 2012 Aug 2012 – Jul 2013 from Aug 2013


1. INSTALL TRANSMISSION CONTROL CABLE BRACKET
  1. Install the control cable bracket with the 2 bolts.

    Torque:
    28 N*m{ 286 kgf*cm , 21 ft.*lbf }


2. INSPECT TORQUE CONVERTER CLUTCH ASSEMBLY

D029376E01

  1. Inspect the one-way clutch.

    1. Install SST in the inner race of the one-way clutch.

      SST
      09350-32014   (09351-32010)

    2. Set SST so that it fits in the notch of the converter hub and in the outer race of the one-way clutch.

      SST
      09350-32014   (09351-32020)

    3. D029377E02
      With the torque converter standing on its side, check that the clutch locks when SST is turned counterclockwise and rotates freely and smoothly when turned clockwise.
      If the results are not as specified, clean the converter and recheck the one-way clutch.
      If the results still are not as specified, replace the converter.

  1. D025367E04
    Determine the condition of the torque converter clutch.

    1. Check that the following conditions are met:

      1. During the stall test or when the shift lever is on N, metallic sounds are not emitted from the torque converter clutch.
      2. The one-way clutch turns in one direction and locks in the other direction.
      3. The amount of powder in the ATF is not greater than the sample shown in the illustration.
      If the results are not as specified, replace the torque converter clutch assembly.

      HINT:
      The sample illustration shows approximately 0.25 liters (0.26 US qts, 0.22 Imp. qts) of the ATF taken from a removed torque converter clutch.

  1. Replace the ATF in the torque converter clutch.

    1. If the ATF is discolored and/or has a foul odor, stir the ATF in the torque converter clutch thoroughly and drain the ATF with the torque converter facing up.

  1. Clean and check the oil cooler and oil pipe line.

    1. If the torque converter clutch is inspected or the ATF is replaced, clean the oil cooler and oil pipe line.

      HINT:
      1. Apply compressed air of 196 kPa (2 kgf/cm2, 28 psi) into the inlet hose.
      2. If a large amount of powder is found in the ATF, add new ATF using a bucket pump and clean the oil cooler and oil pipe line again.

    2. If the ATF is cloudy, inspect the oil cooler (radiator).

  1. D025368E05
    Prevent deformation of the torque converter clutch and damage to the oil pump gear.

    1. When any marks due to interference are found on the end of the bolt for the torque converter clutch and on the bottom of the bolt hole, replace the bolt and torque converter clutch.

    2. All of the bolts should be the same length.

    3. Make sure no spring washers are missing.


3. INSTALL TORQUE CONVERTER CLUTCH ASSEMBLY

  1. C237875
    Engage the spline of the input shaft turbine runner.

  1. C237876
    Engage the spline of the stator shaft and the stator while turning the torque converter assembly.

    HINT:
    If the stator shaft splines are difficult to engage with the stator splines, move the torque converter back approximately 10 mm (0.394 in.) and engage the splines while rotating the torque converter.

  1. C237877
    Turn the torque converter assembly to insert the key of the oil pump drive gear into the groove of the torque converter assembly.

  1. Clean the torque converter set bolt holes.

  1. D025544E01
    Using a vernier caliper and straightedge, measure dimension A between the transmission contact surface of the engine and the torque converter contact surface of the drive plate.

    NOTICE:
    Make sure to deduct the thickness of the straightedge.

  1. D025545E01
    Using a vernier caliper and straightedge, measure dimension B shown in the illustration and check that dimension B is more than dimension A, which was measured in the previous step.

    Standard:
    B = A + 1.00 mm (0.0394 in.) or more

    NOTICE:
    1. Make sure to deduct the thickness of the straightedge.
    2. If the transaxle is installed to the engine with the torque converter not sufficiently inserted, the torque converter may be damaged.


4. INSTALL AUTOMATIC TRANSMISSION ASSEMBLY

  1. C213730E01
    Apply clutch spline grease to the surface of the crankshaft that contacts the torque converter centerpiece.

    Clutch spline grease:
    Toyota Genuine Clutch Spline Grease or equivalent
    Maximum grease amount:
    Approximately 1 g (0.0353 oz.)

    Text in Illustration 
    *1
    Torque Converter Centerpiece
    *2
    Crankshaft

  1. While keeping the engine and automatic transmission assembly horizontal, align the knock pins with the holes in the automatic transmission assembly and Install the 5 bolts.

    Torque:
    71 N*m{ 720 kgf*cm , 53 ft.*lbf }

    NOTICE:
    1. Confirm that the 2 knock pins are installed to the transmission contact surface of the engine cylinder block before installing the automatic transmission assembly.
    2. Do not forcibly pry on the automatic transmission assembly.
    3. Check that the torque converter rotates.


5. INSTALL DRIVE PLATE AND TORQUE CONVERTER SETTING BOLT
  1. Turn the crankshaft to gain access to the installation locations of the 6 drive plate torque converter setting bolts and install each bolt while holding the crankshaft pulley bolt with a wrench.

    Torque:
    48 N*m{ 489 kgf*cm , 35 ft.*lbf }

    NOTICE:
    First install the black colored bolt and then the remaining 5 silver colored bolts.


6. INSTALL STIFFENER PLATE
  1. Install the No. 2 end plate.

  1. Install the No. 4 cylinder block insulator.

  1. Install the stiffener plate LH to the engine and transmission with the 4 bolts.

    Torque:
    71 N*m{ 720 kgf*cm , 53 ft.*lbf }

  1. Install the stiffener plate RH (with clamp tube) to the engine and transmission with the 4 bolts.

    Torque:
    71 N*m{ 720 kgf*cm , 53 ft.*lbf }


7. CONNECT WIRE HARNESS CLAMP BRACKET
  1. Install the wire harness clamp bracket with the bolt.

    Torque:
    13 N*m{ 128 kgf*cm , 9 ft.*lbf }


8. CONNECT ENGINE WIRE
  1. Connect the connectors.

    1. Connect the temperature sensor connector.

    2. Connect the park/neutral position switch connector.

    3. Connect the 3 speed sensor connectors.

    4. Connect the transmission wire connector.


9. INSTALL REAR NO. 1 ENGINE MOUNTING INSULATOR

C238615E01
  1. Install the engine mounting insulator and ground cable to the transmission with the 4 bolts.

    Torque:
    47 N*m{ 479 kgf*cm , 35 ft.*lbf }

    Text in Illustration 
    *1
    Ground Cable
    *a
    Front
    *b
    Upper

    HINT:
    The acceptable installation angle of the ground cable is within 30° upward or downward from the horizontal position.


10. INSTALL NO. 3 FRAME CROSSMEMBER SUB-ASSEMBLY
  1. Install the 4 set bolts of the engine mounting insulator.

    Torque:
    27 N*m{ 275 kgf*cm , 20 ft.*lbf }

  1. Install the frame crossmember with the 4 bolts and 4 nuts.

    Torque:
    50 N*m{ 510 kgf*cm , 37 ft.*lbf }


11. INSTALL STARTER ASSEMBLY
(Click here)

12. CONNECT TRANSMISSION CONTROL SHIFT CABLE ASSEMBLY
  1. Connect the control cable with the new clip.

  1. Connect the control cable with the nut.

    Torque:
    14 N*m{ 143 kgf*cm , 10 ft.*lbf }


13. INSTALL OIL COOLER TUBE

G034255E02
  1. Loosely install the tip of the oil cooler tube inlet to the automatic transmission by hand.

  1. Loosely install the tip of the oil cooler tube outlet to the automatic transmission by hand.

  1. Install the 3 clamps with the 3 bolts.

    Torque:
    for Bolt A and B:
    5.0 N*m{ 51 kgf*cm , 44 in.*lbf }
    for Bolt C:
    12 N*m{ 122 kgf*cm , 9 ft.*lbf }

  1. Using a union nut wrench, disconnect the inlet tube and outlet tube.

    Torque:
    34 N*m{ 350 kgf*cm , 25 ft.*lbf }

    NOTICE:
    Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench (Click here).


14. INSTALL TRANSMISSION OIL FILLER TUBE SUB-ASSEMBLY

G039346E01
  1. Coat a new O-ring with ATF, and install it to the oil filler tube.

  1. Install the oil filler tube with the 2 bolts.

    Torque:
    12 N*m{ 122 kgf*cm , 9 ft.*lbf }

  1. Install the oil dipstick.


15. INSTALL PROPELLER SHAFT WITH CENTER BEARING ASSEMBLY
(Click here)

16. INSTALL FRONT EXHAUST PIPE ASSEMBLY

  1. A111834
    Using a vernier caliper, measure the free length of the compression spring.

    Minimum length:
    40 mm (1.57 in.)

    If the free length is less than the minimum, replace the compression spring.

  1. Install the front pipe to the pipe support.

  1. A111803E01
    Install a new gasket to the outlet pipe.

    NOTICE:
    1. Be careful with the installation direction of the gasket.
    1. Do not reuse the gasket.
    1. To ensure a proper seal, do not use the front pipe to force the gasket onto the outlet pipe.

    HINT:
    Using a plastic-faced hammer, uniformly strike the gasket so that the gasket and outlet pipe are properly fit.

  1. Install the front pipe with the 2 compression springs and 2 bolts. Alternately tighten the bolts in several passes.

    Torque:
    43 N*m{ 438 kgf*cm , 32 ft.*lbf }

    CAUTION:
    Do not reuse the gasket.


17. INSTALL NO. 2 FRAME CROSSMEMBER SUB-ASSEMBLY (except Pre-Runner)
  1. Install the frame crossmember with the 4 bolts and 4 nuts.

    Torque:
    50 N*m{ 510 kgf*cm , 37 ft.*lbf }


18. ADJUST SHIFT LEVER POSITION
(Click here)

19. ADD AUTOMATIC TRANSMISSION FLUID

Fluid type:
Toyota Genuine ATF TYPE T-IV


20. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).


21. INSPECT SHIFT LEVER POSITION
(Click here)

22. CHECK FOR EXHAUST GAS LEAKS

23. CHECK AUTOMATIC TRANSMISSION FLUID
(Click here)

24. INSTALL NO. 2 ENGINE UNDER COVER (for Pre-Runner)

Torque:
28 N*m{ 286 kgf*cm , 21 ft.*lbf }


25. INSTALL NO. 1 ENGINE UNDER COVER (for Pre-Runner)

Torque:
28 N*m{ 286 kgf*cm , 21 ft.*lbf }

← INSTALLATION (Jun 2011 – Jul 2012)INSTALLATION (from Aug 2013) →