INSTALLATION
Removal / installation · Vehicles built Aug 2012 – Jul 2013
Versions by build date: Jun 2011 – Jul 2012 Aug 2012 – Jul 2013 from Aug 2013
| 1. INSTALL STARTER ASSEMBLY |
Connect the ground cable and install the starter with the 2 nuts and bolt.

- Torque:
- 68 N*m{ 693 kgf*cm , 50 ft.*lbf }
- HINT:
- Make sure to connect the ground cable with the nut as shown in the illustration.
Install the starter wire to terminal 30 with the nut.
- Torque:
- 21 N*m{ 214 kgf*cm , 15 ft.*lbf }
Connect the starter connector.
| 2. INSTALL CLUTCH RELEASE CYLINDER ASSEMBLY (for Manual Transmission) |
![]() ![]() |
Install the release cylinder with the 2 bolts.
- Torque:
- 12 N*m{ 120 kgf*cm , 9 ft.*lbf }
| 3. INSTALL FRONT FENDER SEAL |
Install the seal with the 5 clips.
| 4. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
- NOTICE:
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).