2014 Hilux · Service Manual ENGINE

INSTALLATION

Removal / installation · Vehicles built Aug 2012 – Jul 2013

Versions by build date: Jun 2011 – Jul 2012 Aug 2012 – Jul 2013 from Aug 2013


1. INSTALL DIESEL THROTTLE BODY ASSEMBLY

A111832
  1. Install a new gasket and the throttle body with the 2 bolts and 2 nuts.

    Torque:
    20 N*m{ 204 kgf*cm , 15 ft.*lbf }

  1. A111790
    Connect the 2 connectors.


2. INSTALL NO. 2 AIR CLEANER PIPE SUB-ASSEMBLY (w/o Intercooler)

A111789
  1. Connect the pipe (with the 2 air hoses) and install the bolt.

    Torque:
    20 N*m{ 204 kgf*cm , 15 ft.*lbf }

  1. Tighten the 2 clamps.

  1. Connect the vacuum hose to the gas filter.

  1. Connect the manifold absolute pressure sensor connector.


3. INSTALL INTERCOOLER ASSEMBLY
(Click here)