ECD SYSTEM (for i-ART) > ECM Power Source Circuit |

| 1.INSPECT ECM (+B AND +B2 VOLTAGE) |
Turn the ignition switch to ON.
![]() |
Measure the voltage according to the value(s) in the table below.
| Tester Connection | Switch Condition | Specified Condition |
| E32-24 (+B) - E28-6 (E1) | Ignition switch ON | 11 to 14 V |
| E32-17 (+B2) - E28-6 (E1) | Ignition switch ON | 11 to 14 V |
| *a | Component with harness connected (ECM) |
|
| ||||
| NG | |
| 2.CHECK HARNESS AND CONNECTOR (ECM - BODY GROUND) |
Disconnect the ECM connector.
Measure the resistance according to the value(s) in the table below.
| Tester Connection | Condition | Specified Condition |
| E28-6 (E1) - Body ground | Always | Below 1 Ω |
Reconnect the ECM connector.
|
| ||||
| OK | |
| 3.INSPECT ECM (IGSW VOLTAGE) |
![]() |
Turn the ignition switch to ON.
Measure the voltage according to the value(s) in the table below.
| Tester Connection | Switch Condition | Specified Condition |
| E31-24 (IGSW) - E28-6 (E1) | Ignition switch ON | 11 to 14 V |
| *a | Component with harness connected (ECM) |
|
| ||||
| OK | |
| 4.INSPECT ECM (MREL VOLTAGE) |
![]() |
Turn the ignition switch to ON.
Measure the voltage according to the value(s) in the table below.
| Tester Connection | Switch Condition | Specified Condition |
| E31-11 (MREL) - E28-6 (E1) | Ignition switch ON | 11 to 14 V |
| *a | Component with harness connected (ECM) |
|
| ||||
| OK | |
| 5.INSPECT NO. 1 INTEGRATION RELAY (MAIN RELAY) |
Inspect the No. 1 integration relay (MAIN relay) .
|
| ||||
| OK | |
| 6.CHECK HARNESS AND CONNECTOR (MAIN RELAY - ECM, MAIN RELAY - BODY GROUND) |
Check the harness and connector between the No. 1 integration relay (MAIN relay) and ECM.
Remove the No. 1 integration relay from the engine room relay block and junction block assembly.
Disconnect the ECM connector.
Measure the resistance according to the value(s) in the table below.
| Tester Connection | Condition | Specified Condition |
| 1J-4 - E32-24 (+B) | Always | Below 1 Ω |
| 1J-5 - E32-17 (+B2) | Always | Below 1 Ω |
| 1J-2 - E31-11 (MREL) | Always | Below 1 Ω |
| 1J-4 or E32-24 (+B) - Body ground | Always | 10 kΩ or higher |
| 1J-5 or E32-17 (+B2) - Body ground | Always | 10 kΩ or higher |
| 1J-2 or E31-11 (MREL) - Body ground | Always | 10 kΩ or higher |
Reconnect the ECM connector.
Reinstall the No. 1 integration relay.
Check the harness and connector between the No. 1 integration relay (MAIN relay) and body ground.
Remove the No. 1 integration relay from the engine room relay block and junction block assembly.
Measure the resistance according to the value(s) in the table below.
| Tester Connection | Condition | Specified Condition |
| 1J-3 - Body ground | Always | Below 1 Ω |
Reinstall the No. 1 integration relay.
|
| ||||
| OK | ||
| ||
| 7.INSPECT IGNITION SWITCH |
Inspect the ignition switch (Click here).
|
| ||||
| OK | ||
| ||