INSPECTION
Inspection · Vehicles built from Aug 2013
| INSPECT TIE ROD END SUB-ASSEMBLY |
Install the nut.

Flip the ball joint stud back and forth 5 times as shown in the illustration.
Using a torque wrench, turn the nut continuously at a rate of 3 to 5 seconds per turn and check the torque reading on the 5th turn.
- Standard Torque:
- 1.0 to 3.9 N*m (10 to 39 kgf*cm, 9 to 34 in.*lbf)
| INSPECT TOTAL PRELOAD |
Place matchmarks as shown in the illustration.

Text in Illustration *a
Matchmark
Temporarily install the 2 steering rack ends to the steering rack.
- NOTICE:
- Do not fully turn the steering rack without the steering rack ends installed as it may damage the oil seal in the rack housing.
Using SST, fully turn the steering rack right and left 10 times to settle it.

- SST
- 09616-00011
Using SST, turn the control valve and measure the preload.

- SST
- 09616-00011
- Standard preload (turning):
Body Type
Engine Type
Specified Condition
for 5 Door
for 1GR, 2TR and 1KD
1.6 to 2.3 N*m (16 to 23 kgf*cm, 14 to 20 in.*lbf)
for 5L
1.5 to 2.2 N*m (15 to 22 kgf*cm, 13 to 19 in.*lbf)
for 3 Door
for 1KD and 2TR
- HINT:
- Measure the standard preload at the steering rack neutral point.
- The steering control valve is fully turned when turned 3.0 times. Half of the distance from the fully turned position is the neutral point.
- Measure the standard preload at the steering rack neutral point.
After inspecting the preload, align the matchmarks.