2013-2015 Land Cruiser Prado · Service Manual Vehicle Interior

INSTALLATION

Removal / installation · Vehicles built from Aug 2014

Versions by build date: Aug 2013 – Jul 2014 from Aug 2014

HINT:
  1. Use the same procedure for RHD and LHD vehicles.
  2. The procedure listed below is for LHD vehicles.


1. INSTALL COMBINATION METER ASSEMBLY
  1. Connect the 2 connectors.

  1. Install the combination meter assembly with the 4 screws.


2. INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY
  1. Connect the connector.

  1. Attach the 2 clips and 2 guides.

  1. Attach the 4 claws.

  1. Attach the 4 claws to install the instrument cluster finish panel sub-assembly.


3. INSTALL LOWER INSTRUMENT PANEL FINISH PANEL ASSEMBLY
  1. Connect each connector.

  1. Attach the 4 clips to install the instrument panel finish panel.


4. INSTALL INSTRUMENT PANEL FINISH PLATE GARNISH (for RHD)
  1. Connect each connector.

  1. Attach the 4 clips to install the instrument panel finish plate garnish.


5. INSTALL INSTRUMENT CLUSTER FINISH PANEL ORNAMENT (for LHD)
  1. Attach the 3 clips to install the instrument cluster finish panel ornament.


6. CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).


7. RESTORE AUTOAWAY/RETURN FUNCTION (for Power Tilt and Power Telescopic Steering Column)
  1. Restore the Autoaway/Return function setting to the previous condition by changing the customize parameter (Click here).