INSPECTION
Inspection · Vehicles built from Sep 2011
| INSPECT TIE ROD END SUB-ASSEMBLY LH |
 |
Install the nut.
Flip the ball joint stud back and forth 5 times as shown in the illustration.
Using a torque wrench, turn the nut continuously at a rate of 3 to 5 seconds per turn and check the torque reading on the 5th turn.
- Torque:
- 0.98 to 3.92 N*m (10.0 to 35.0 kgf*cm, 8.67 to 30.36 in.*lbf)
| INSPECT TOTAL PRELOAD |
 |
- Put matchmarks on the dust cover and steering link.
Remove the dust cover.
Temporarily install the 2 steering rack ends to the power steering rack.
- NOTICE:
- Do not fully turn the power steering rack without the steering rack ends as it may damage the oil seal in the rack housing.
- Using SST, fully turn the power steering rack right and left 10 times to settle it.
- SST
- 09616-00011
- Using SST, turn the control valve and measure the preload.
- SST
- 09616-00011
- Standard preload (turning):
- 2.05 to 2.85 N*m (21.0 to 29.0 kgf*cm, 19 to 25 in.*lbf)
If the turning torque is not as specified, replace the power steering link.
- NOTICE:
- After setting the steering rack to the neutral point, align the dust cover rib with the power steering protrusion.
- HINT:
- Measure the standard preload at the steering rack neutral point.
- The steering control valve is fully turned when turned 3.14 times. Half of the distance from the fully turned position is the neutral point.
- After inspecting the preload, align the matchmarks and install the dust cover.