11363A
1.INSTALL FLYWHEEL HOUSING SIDE COVER
Install the flywheel housing side cover to the cylinder block.
28100
2.INSTALL STARTER ASSEMBLY
Install the starter assembly with the 2 bolts.
Connect the starter connector.
Connect the starter wire with the nut.
Connect the terminal cap.
33823
3.INSTALL NO. 1 TRANSMISSION CONTROL CABLE BRACKET (for CVT)
33820B
4.CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY (for CVT)
Connect the transmission control cable assembly to the No. 1 transmission control cable bracket with a new clip.
74414B
5.INSTALL BATTERY BRACKET REINFORCEMENT
Install the battery bracket reinforcement with the 2 bolts.
74417
6.INSTALL FRONT BATTERY BRACKET
Install the front battery bracket with the 4 bolts.
Attach the 3 wire harness clamps.
16057
7.CONNECT RADIATOR HOSE SUB-ASSEMBLY
Connect the radiator hose sub-assembly to the front battery bracket with the 2 bolts.
74431
8.INSTALL BATTERY TRAY
28800
9.INSTALL BATTERY
74404A
10.INSTALL BATTERY CLAMP SUB-ASSEMBLY
Attach the hook of the battery clamp sub-assembly to the front battery bracket.
Partially tighten the nut and temporarily install the bolt.
Adjust the battery clamp sub-assembly position.
Tighten the nut and bolt.
17705
11.INSTALL AIR CLEANER CAP SUB-ASSEMBLY
12.CONNECT CABLE TO POSITIVE BATTERY TERMINAL
13.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION
11212
14.INSTALL NO. 2 CYLINDER HEAD COVER
51441
15.INSTALL NO. 1 ENGINE UNDER COVER