Home › Power Source / Network › G16E-GTS (BATTERY / CHARGING) › GENERATOR › from 2020.09
RM36W0E _57 Power Source / Network _095208 G16E-GTS BATTERY / CHARGING _0449418 GENERATOR A

G16E-GTS BATTERY / CHARGING  GENERATOR  INSTALLATION  


PROCEDURE

Hide 27020 1.INSTALL GENERATOR WITH REGULATOR ASSEMBLY

a.

Temporarily install the generator with regulator assembly.


b.

Using an E8 "TORX" socket wrench, install the 2 stud bolts.

Torque:
9.8 N*m (100 kgf*cm, 87 in.*lbf)


c.

Install the bolt.

Torque:
25 N*m (255 kgf*cm, 18 ft.*lbf)


d.

Install the generator splash guard cover assembly to the generator with regulator assembly with the 2 nuts.

Torque:
25 N*m (255 kgf*cm, 18 ft.*lbf)


e.

Connect the wire harness to terminal B with the nut.

Torque:
9.8 N*m (100 kgf*cm, 87 in.*lbf)


f.

Close the terminal cap.


g.

Connect the 3 connector.


h.

Engage the clamp.


Hide 16361A 2.INSTALL V-RIBBED BELT

Hide 3.CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL

Hide 4. INITIALIZATION AFTER RECONNECTING AUXILIARY BATTERY TERMINAL

Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>WORK PROCEDURE

HINT:

When disconnecting and reconnecting the battery, there is an automatic learning function thatcompletes learning when the respective system is used.

Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>AUTOMATIC LEARNING CHART