REPLACEMENT
Removal / installation · Vehicles built from Nov 2005
| 1. INSPECT VALVE GUIDE BUSHING OIL CLEARANCE |
![]() ![]() |
Using a caliper gauge, measure the internal diameter of the valve guide bushing.
- Bushing inside diameter:
- 6.010 to 6.030 mm (0.2366 to 0.2374 in.)
Subtract the valve stem diameter measurement from the internal diameter measurement of the valve guide bushing.
- Standard oil clearance:
- 0.025 to 0.060 mm (0.0010 to 0.0024 in.) for intake
0.003 to 0.065 mm (0.0012 to 0.0026 in.) for exhaust
- Maximum oil clearance:
- 0.08 mm (0.0031 in.) for intake
0.10 mm (0.0039 in.) for exhaust
| 2. REMOVE INTAKE VALVE GUIDE BUSHING |
![]() ![]() |
Heat the cylinder head to between 80 and 100°C.
Using SST and a hammer, tap out the valve guide bushing to the combustion chamber side.
- SST
- 09201-10000
09950-70010
| 3. REMOVE EXHAUST VALVE GUIDE BUSHING |
![]() ![]() |
Heat the cylinder head to between 80 and 100°C.
Using SST and a hammer, tap out the valve guide bushing to the combustion camber side.
- SST
- 09201-10000
09950-70010
| 4. INSTALL INTAKE VALVE GUIDE BUSHING |
![]() ![]() |
Using a caliper gauge, measure the bushing bore diameter of the cylinder head.
- Diameter:
- 10.985 to 11.006 mm (0.4325 to 0.4333 in.)
- HINT:
- If the bushing bore diameter is as specified, install the standard busing.
- If the bushing bore diameter is not as specified, correct it to 11.035 to 11.056 mm (0.4345 to 0.4353 in.) and install the oversize bushing.
Bushing size
Bushing bore diameter mm (in.)
Standard
Standard 10.985 to 11.006 (0.4325 to 0.4333)
Over size (0.05)
Over size 11.035 to 11.056 (0.4345 to 0.4353)
- If the bushing bore diameter is as specified, install the standard busing.
Heat the cylinder head to between 80 and 100°C.
Using SST and a hammer, tap in a new valve guide bushing to the specified protrusion height.

- SST
- 09201-10000
09950-70010
- Protrusion height:
- 11.2 to 11.6 mm (0.441 to 0.457 in.)
Using a reamer, ream the inside of the valve guide bushing to the specified oil clearance between the valve guide bushing and valve stem.

- Standard oil clearance:
- 0.025 to 0.060 mm (0.0010 to 0.0024 in.)
| 5. INSTALL EXHAUST VALVE GUIDE BUSHING |
![]() ![]() |
Using a caliper gauge, measure the bushing bore diameter of the cylinder head.
- Diameter:
- 10.985 to 11.006 mm (0.0010 to 0.0024 in.)
- HINT:
- If the bushing bore diameter is as specified, install the standard bushing.
- If the bushing bore diameter is not as specified, correct it to 11.035 to 11.056 mm (0.4345 to 0.4353 in.) and install the oversize bushing.
Bushing size
Bushing bore diameter mm (in.)
Standard
Standard 10.985 to 11.006 (0.4325 to 0.4333)
Over size (0.05)
Over size 11.035 to 11.056 (0.4345 to 0.4353)
- If the bushing bore diameter is as specified, install the standard bushing.
Heat the cylinder head to between 80 and 100°C.
Using SST and a hammer, tap in a new valve guide bushing to the specified protrusion height.

- SST
- 09201-10000
09950-70010
- Protrusion height:
- 11.2 to 11.6 mm (0.441 to 0.457 in.)
Using a reamer, ream the inside of the valve guide bushing to the specified oil clearance between the valve guide bushing and valve stem.

- Standard oil clearance:
- 0.030 to 0.065 mm (0.0012 to 0.0023 in.)