1.INSTALL DIESEL THROTTLE BODY
Remove any seal packing material from the contact surface.
| *a | 70 mm (2.75 in.) |
| *b | Seal Packing |
Apply a continuous bead of seal packing (width: 1.5 to 2.5 mm (0.0591 to 0.0984 in.)) as shown in the illustration.
Toyota Genuine Seal Packing Black, Three Bond 1207B or equivalent
Remove any oil from contact surface.
Install the diesel throttle body within 3 minutes of applying the seal packing.
Do not run the engine for at least 2 hours after installation.
Install the diesel throttle body with the 2 bolts and 2 nuts.
Connect the 2 connectors.
17030
2.INSTALL AIR HOSE ASSEMBLY
| *a | Upper Side |
| *b | RH Side |
Connect the air hose assembly and install the bolt.
Tighten the hose clamp (intercooler air hose side) as shown in the illustration.
Tighten the screw at a rate of 2 seconds per turn.
Tighten the hose clamp (diesel throttle body side) as shown in the illustration.
Do not remove the hose clamp A.
Attach the 2 clamps and then connect the vacuum transmitting hose.
11409
3.INSTALL ENGINE OIL LEVEL DIPSTICK GUIDE
44379A
4.INSTALL NO. 2 OIL RESERVOIR BRACKET
44360
5.INSTALL VANE PUMP OIL RESERVOIR ASSEMBLY
53712C
6.INSTALL FRONT FENDER APRON LH
Install the front fender apron LH with the 6 bolts.
51441D
7.INSTALL NO. 1 ENGINE UNDER COVER
58701A
8.INSTALL FRONT ENGINE SERVICE COVER PANEL SUB-ASSEMBLY
33820B
9.CONNECT TRANSMISSION CONTROL CABLE ASSEMBLY
58841A
10.INSTALL SHIFTING HOLE COVER (for Automatic Transmission)
58123A
11.INSTALL SHIFT AND SELECT LEVER SUPPORT WITH BOOTS (for Manual Transmission)
58420
12.INSTALL NO. 2 ENGINE SERVICE HOLE COVER ASSEMBLY
58734B
13.INSTALL REAR ENGINE SERVICE COVER WEATHERSTRIP
58410
14.INSTALL ENGINE SERVICE HOLE COVER
58521D
15.INSTALL ENGINE SERVICE HOLE COVER MAT
16. PERFORM INITIALIZATION