When replacing the injectors (including shuffling the injectors between the cylinders), common rail or cylinder head, it is necessary to replace the injection pipes with new ones.
When replacing the fuel supply pump, common rail, cylinder block, cylinder head, cylinder head gasket or timing gear case, it is necessary to replace the fuel inlet pipe with a new one.
After removing the injection pipes, clean them with a brush and compressed air.
1.INSTALL NO. 2 EGR VALVE ASSEMBLY (w/ EGR Cooler)
Using a 6 mm hexagon wrench, install the EGR valve adapter, No. 2 EGR valve, EGR cooler, 2 new gaskets, 3 plate washers with the 3 hexagon bolts.
Using a 5 mm hexagon wrench, install the bolt labeled A.
| *1 | EGR Cooler | *2 | New Gasket |
| *3 | No. 2 EGR Valve | *4 | EGR Valve Adapter |
2.INSTALL ELECTRIC EGR CONTROL VALVE ASSEMBLY
w/ EGR Cooler:
Install a new gasket and electric EGR control valve to the EGR valve adapter with the 2 bolts.
Make sure the claws of the gasket face the electric EGR control valve.
| *1 | EGR Cooler | *2 | New Gasket |
| *3 | Electric EGR Control Valve | *4 | Claw |
w/o EGR Cooler:
Install a new gasket and the electric EGR control valve.
3.INSTALL NO. 1 EGR PIPE SUB-ASSEMBLY (w/o EGR Cooler)
| *1 | Claw |
Install 2 new gaskets and the No. 1 EGR pipe with the 2 nuts and 2 bolts.
Make sure the claws of the gasket face the No. 1 EGR pipe.
4.TEMPORARILY INSTALL ELECTRIC EGR CONTROL VALVE ASSEMBLY WITH NO. 2 EGR VALVE AND EGR COOLER (w/ EGR Cooler)
Set a new gasket to the cylinder head.
| *1 | New Gasket |
Temporarily install the electric EGR control valve with No. 2 EGR valve and EGR cooler with the 2 nuts and bolt.
Temporarily install the bolt so that the bolt head contacts the EGR cooler.
Connect the vacuum hose to the No. 2 EGR valve.
Connect the EGR valve position sensor connector.
5.INSTALL NO. 2 INTAKE AIR CONNECTOR (w/ EGR Cooler)
Set a new gasket labeled A to the No. 2 intake air connector as shown in the illustration.
Insert the No. 2 intake air connector with the gasket into the electric EGR control valve.
Install a new gasket labeled B to the electric EGR control valve side shown in the illustration.
6.TEMPORARILY INSTALL INTAKE AIR CONNECTOR (w/ EGR Cooler)
Set a new gasket labeled C to the intake manifold.
Temporarily install the intake air connector to the intake manifold with the 3 bolts.
Temporarily install the intake air connector and electric EGR control valve with the 3 nuts shown in the illustration.
| *1 | No. 2 Intake Air Connector | *2 | New Gasket |
| *3 | Intake Air Connector | - | - |
7.TIGHTEN NO. 2 INTAKE AIR CONNECTOR AND INTAKE AIR CONNECTOR (w/ EGR Cooler)
Tighten the 3 nuts labeled A shown in the illustration.
8.TIGHTEN INTAKE AIR CONNECTOR AND INTAKE MANIFOLD (w/ EGR Cooler)
Tighten the 3 bolts labeled B shown in the illustration.
9.TIGHTEN EGR COOLER (w/ EGR Cooler)
Tighten the bolt labeled C shown in the illustration.
Tighten the 2 nuts labeled D shown in the illustration.
10.INSTALL INTAKE AIR CONNECTOR (w/o EGR Cooler)
11.INSTALL NO. 2 INTAKE AIR CONNECTOR BRACKET (w/o EGR Cooler)
12.INSTALL NO. 2 INTAKE AIR CONNECTOR BRACKET (w/ EGR Cooler)
Temporarily install the No. 2 intake air connector bracket with the 3 bolts.
Tighten the bolt labeled A.
Tighten the 2 bolts labeled B.
13.INSTALL ELECTRIC VACUUM REGULATING VALVE ASSEMBLY
14.INSTALL NO. 1 GAS FILTER WITH GAS FILTER BRACKET (w/ EGR Cooler)
15.CONNECT NO. 3 WATER BY-PASS PIPE (w/ EGR Cooler)
Connect the No. 3 water by-pass pipe with wire harness with the 2 bolts.
16.INSTALL NO. 1, NO. 2 AND NO. 3 INJECTION PIPE SUB-ASSEMBLY (w/ EGR Cooler)
17.CONNECT NO. 4 WATER BY-PASS HOSE (w/ EGR Cooler)
| *1 | Lower Side |
| *2 | Upper Side |
| *3 | LH Side |
Connect the No. 4 water by-pass hose to the EGR cooler.
The direction of the hose clamp is indicated in the illustration.
Insert the outlet hose into the stopper.
18.CONNECT NO. 3 WATER BY-PASS HOSE (w/ EGR Cooler)
Connect the No. 3 water by-pass hose to the EGR cooler.
The direction of the hose clamp is indicated in the illustration.
Insert the outlet hose into the stopper.
Install the clamp.
19.INSTALL DIESEL THROTTLE BODY ASSEMBLY
20.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page General>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION).
21.ADD ENGINE COOLANT (w/ EGR Cooler)
22. BLEED AIR FROM FUEL SYSTEM (w/ EGR Cooler)
23.INSPECT FOR COOLANT LEAK (w/ EGR Cooler)
24.INSPECT FOR FUEL LEAK (w/ EGR Cooler)