Tightening torque for "Major areas involving basic vehicle performance such as moving/turning/stopping" : N*m (kgf*cm, ft.*lbf) |
|
N*m (kgf*cm, ft.*lbf): Specified torque |
| * | For use with SST or union nut wrench | ● | Non-reusable part |
| *1 | NO. 1 HYDROGEN SUPPLY REGULATOR PLUG | *2 | O-RING |
|
Tightening torque for "Major areas involving basic vehicle performance such as moving/turning/stopping" : N*m (kgf*cm, ft.*lbf) | * | For use with SST |
| ● | Non-reusable part |
|
TOYOTA Genuine FC Grease |
| *1 | HOSE CLAMP | - | - |
|
N*m (kgf*cm, ft.*lbf): Specified torque | - | - |
77AE1
1.INSTALL HYDROGEN INLET RECEPTACLE
|
|
| *a | Torque Wrench Fulcrum Length | - | - |
Using SST turn counterclockwise to tighten the hydrogen inlet receptacle while holding the hydrogen inlet receptacle bracket sub-assembly by hand.
67.5 N*m (688 kgf*cm, 50 ft.*lbf)
Calculate the torque wrench reading when changing the fulcrum length of the torque wrench.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>PRECAUTION
When using SST (fulcrum length of 133 mm (5.24 in.)) + torque wrench (fulcrum length of 380 mm (15.0 in.)): 50 N*m (510 kgf*cm, 37 ft.*lbf)
77AE6
2.INSTALL NO. 1 HYDROGEN INLET RECEPTACLE BRACKET CUSHION
| *1 | No. 1 Hydrogen Inlet Receptacle Bracket Cushion | *2 | Hydrogen Inlet Receptacle Bracket Sub-assembly |
| *a | Correct | *b | Incorrect |
| *c | A portion | - |
Install the No. 1 hydrogen inlet receptacle bracket cushion to the hydrogen inlet receptacle bracket sub-assembly as shown in the illustration.
Make sure the No. 1 hydrogen inlet receptacle bracket cushion does not ride up on the A portion of the hydrogen inlet receptacle bracket sub-assembly.
77A0E
3.INSTALL HYDROGEN INLET RECEPTACLE BRACKET SUB-ASSEMBLY
Temporarily install the hydrogen inlet receptacle bracket sub-assembly with the 4 bolts.
Tighten the 4 bolts.
Attach the clamp and connect the hydrogen control wire.
77BA1
4.CONNECT NO. 1 HYDROGEN TANK TUBE
|
|
| *a | Torque Wrench Fulcrum Length | - | - |
To prevent contamination by foreign matter, remove the plastic bags from the openings of the No. 1 hydrogen tank tube immediately before performing the procedure.
When frost has formed on the hydrogen tank assembly or piping, water droplets may be formed when the frost begins to melt. If water droplets enter the tank or piping, it could result in blockage of the hydrogen piping, so do not allow water droplets to enter the tank or piping.
To prevent contamination by foreign matter, remove the protective tape from the openings of the hydrogen inlet receptacle immediately before performing the procedure.
Temporarily install the No. 1 hydrogen tank tube to the hydrogen inlet receptacle with the union nut.
Using a 19 mm union nut wrench, tighten the union nut while holding a tube part by hand.
25 N*m (255 kgf*cm, 18 ft.*lbf)
Calculate the torque wrench reading when changing the fulcrum length of the torque wrench.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>PRECAUTION
When using a union nut wrench (fulcrum length of 30 mm (1.18 in.)) + torque wrench (fulcrum length of 180 mm (7.09 in.)): 21.4 N*m (218 kgf*cm, 16 ft.*lbf)
65638
5.INSTALL REAR WHEEL HOUSE LINER LH
75866E
6.INSTALL ROCKER PANEL MOULDING PROTECTOR LH
898D1
7.INSTALL HYDROGEN FUEL CONTROL TRANSMITTER
77305A
8.INSTALL FUEL FILLER OPENING LID SUB-ASSEMBLY
9.CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
10. FIRST LEAK CHECK
17DB3
11.INSTALL NO. 3 FC EXHAUST PIPE
12. INITIALIZATION AFTER RECONNECTING BATTERY TERMINAL
Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>WORK PROCEDURE
When disconnecting and reconnecting the battery, there is an automatic learning function that completes learning when the respective system is used.
Click hereGeneral>SETUP>WHEN DISCONNECTING OR RECONNECTING BATTERY TERMINAL>AUTOMATIC LEARNING CHART
13. SECOND LEAK CHECK
58398F
14.INSTALL NO. 1 FLOOR UNDER COVER
57628E
15.INSTALL REAR FLOOR SIDE MEMBER COVER LH
58403L
17.INSTALL REAR NO. 3 FLOOR BOARD SUB-ASSEMBLY
58404B
18.INSTALL REAR NO. 4 FLOOR BOARD SUB-ASSEMBLY