INSTALLATION
Removal / installation · Vehicles built from Jan 2012
Versions by build date: Sep 2011 – Dec 2011 from Jan 2012
| 1.
INSTALL COMBINATION METER ASSEMBLY |
 |
- Connect the connectors.
- Install the combination meter with the 4 screws.
| 2.
INSTALL INSTRUMENT CLUSTER FINISH PANEL SUB-ASSEMBLY |
 |
- Attach the 9 claws to install the finish panel.
- Attach the 4 claws.
| 3.
INSTALL NO. 2 INSTRUMENT CLUSTER FINISH PANEL GARNISH
|
 |
- Attach the 2 claws to install the panel garnish.
| 4.
INSTALL LOWER INSTRUMENT PANEL PAD SUB-ASSEMBLY LH |
 |
w/ Entry and Start System:
(Click here)
w/o Entry and Start System:
(Click here)
| 5.
INSTALL NO. 2 INSTRUMENT PANEL FINISH PANEL CUSHION
|
 |
- Attach the 7 claws to install the panel cushion.
| 6.
INSTALL NO. 1 INSTRUMENT CLUSTER FINISH PANEL GARNISH
|
 |
- Attach the 3 claws to install the panel garnish.
| 7.
CONNECT CABLE TO NEGATIVE BATTERY TERMINAL |
 |
- NOTICE:
- Reset the Autoaway/Return function setting to the previous condition by changing the customize parameter (Click here).
- When disconnecting the cable, some systems need to be initialized after the cable is reconnected (Click here).