89111
1.INSTALL NETWORK GATEWAY ECU
|
Install in this Direction |
Attach the claw to install the network gateway ECU.
82877
2.INSTALL ECU INTEGRATION BOX RH
|
Nut |
|
Bolt |
Install the ECU integration box RH with the 2 nuts and bolt.
Attach the claw and relay holder.
w/ Clearance Warning System:
Connect the connector.
| *a | w/ Clearance Warning System |
Attach the wire harness clamp.
w/ Clearance Warning System:
Connect the 5 connectors.
w/o Clearance Warning System:
Connect the 4 connectors.
55308B
3.INSTALL NO. 3 INSTRUMENT PANEL TO COWL BRACE SUB-ASSEMBLY
|
Nut |
|
Bolt |
Install the No. 3 instrument panel to cowl brace sub-assembly with the nut and bolt.
Attach the 2 wire harness clamps.
73900
4.INSTALL LOWER NO. 1 REMOVE INSTRUMENT PANEL AIRBAG ASSEMBLY
5.CONNECT CABLE TO NEGATIVE AUXILIARY BATTERY TERMINAL
for A25A-FKS:
for M20A-FKS:
for A25A-FXS:
Click hereGeneral>MAINTENANCE>A25A-FXS AUXILIARY BATTERY>INSTALLATION
When disconnecting the cable, some systems need to be initialized after the cable is reconnected.
Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION
65351A
6.INSTALL BATTERY HOLE COVER (for HV Model)
58416K
7.INSTALL REAR NO. 2 FLOOR BOARD (for HV Model)
58410B
8.INSTALL DECK BOARD ASSEMBLY (for HV Model)
9. PERFORM DIAGNOSTIC SYSTEM CHECK
for HV Model with Occupant Classification System:
for Gasoline Model with Occupant Classification System:
w/o Occupant Classification System:
10.CHECK SRS WARNING LIGHT
for HV Model with Occupant Classification System:
for Gasoline Model with Occupant Classification System:
w/o Occupant Classification System: