1.INSTALL TRANSMISSION CONTROL CABLE BRACKET
Install the control cable bracket with the 2 bolts.
2.INSPECT TORQUE CONVERTER ASSEMBLY
3.INSTALL TORQUE CONVERTER ASSEMBLY
Engage the spline of the input shaft turbine runner.
Engage the spline of the stator shaft and the stator while turning the torque converter assembly.
If the stator shaft spline are difficult to engage with the stator splines, move the torque converter back approximately 10 mm (0.787 in.) and engage the splines while rotating the torque converter.
Turn the torque converter assembly to insert the key of the oil pump drive gear into the groove of the torque converter assembly.
Clean the torque converter set bolt holes.
Using a vernier caliper and straightedge, measure dimension A between the transaxle contact surface of the engine and the torque converter contact surface of the drive plate.
Make sure to deduct the thickness of the straightedge.
Using a vernier caliper and straightedge, measure dimension B shown in the illustration and check that dimension B is more than dimension A, which was measured in the previous step.
B = A + 1.00 mm (0.0394 in.) or more
Make sure to deduct the thickness of the straightedge.
If the transaxle is installed to the engine with the torque converter not sufficiently inserted, the torque converter may be damaged.
4.INSTALL AUTOMATIC TRANSMISSION ASSEMBLY
| *1 | Torque Converter Centerpiece |
| *2 | Crankshaft |
Apply clutch spline grease to the surface of the crankshaft that contacts the torque converter centerpiece.
Toyota Genuine Clutch Spline Grease or equivalent
Approximately 1 g (0.0353 oz.)
While keeping the engine and automatic transmission assembly horizontal, align the knock pins with the holes in the automatic transmission assembly and Install the 5 bolts.
Confirm that the 2 knock pins are installed to the transaxle contact surface of the engine cylinder block before installing the automatic transmission assembly.
Do not forcibly pry on the automatic transmission assembly
Check that the torque converter rotates.
Hold the crankshaft pulley bolt with a wrench and install the 6 drive plate and torque converter setting bolts.
First install the black colored bolt and then the remaining 5 silver colored bolts.
5.INSTALL STIFFENER PLATE
Install the No. 2 end plate.
Install the No. 4 cylinder block insulator.
Install the stiffener plate LH to the engine and transmission with the 4 bolts.
Install the stiffener plate RH (with clamp tube) to the engine and transmission with the 4 bolts.
6.INSTALL WIRE HARNESS CLAMP BRACKET
Install the wire harness clamp bracket with the bolt.
7.CONNECT ENGINE WIRE
Connect the connectors.
Connect the temperature sensor connector.
Connect the park/neutral position switch connector.
Connect the 3 speed sensor connectors.
Connect the transmission wire connector.
8.INSTALL REAR NO. 1 ENGINE MOUNTING INSULATOR
Install the engine mounting insulator to the transmission with the 4 bolts.
9.INSTALL NO. 3 FRAME CROSSMEMBER SUB-ASSEMBLY
Install the 4 set bolts of the engine mounting insulator.
Install the frame crossmember with the 4 bolts and 4 nuts.
10.INSTALL STARTER ASSEMBLY
11.CONNECT GROUND CABLE
Connect the earth wire with the nut.
12.CONNECT TRANSMISSION CONTROL SHIFT CABLE ASSEMBLY
Connect the control cable with a new clip.
Connect the control cable with the nut.
13.INSTALL OIL COOLER TUBE
Loosely install the tip of the oil cooler tube inlet to the automatic transmission by hand.
Loosely install the tip of the oil cooler tube outlet to the automatic transmission by hand.
Install the 3 clamps with the 3 bolts.
Using a union nut wrench, tighten the inlet and outlet tubes.
Use the formula to calculate special torque values for situations where a union nut wrench is combined with a torque wrench (See page General>INTRODUCTION>REPAIR INSTRUCTION>PRECAUTION).
14.INSTALL TRANSMISSION OIL FILLER TUBE SUB-ASSEMBLY
Coat a new O-ring with ATF, and install it to the oil filler tube.
Install the oil filler tube with the 2 bolts.
Install the oil dipstick.
15.INSTALL PROPELLER SHAFT ASSEMBLY
16.INSTALL FRONT PROPELLER SHAFT ASSEMBLY
17.INSTALL FRONT EXHAUST PIPE ASSEMBLY
18.INSTALL TRANSFER HIGH AND LOW SHIFT LEVER ASSEMBLY
| *1 | Select Return Spring |
While pushing the select return spring to the left with the end of the transfer high and low shift lever, insert the end of the shift lever into the shift fork.
| *1 | Shift Lever Cap |
While holding down the shift lever cap, install the snap ring to install the transfer high and low shift lever.
Return the transfer front drive shift boot to its original position.
19.INSTALL SHIFT LEVER BOOT ASSEMBLY
Install the shift lever boot with the 4 screws.
20.ADJUST SHIFT LEVER POSITION
21.ADD AUTOMATIC TRANSMISSION FLUID
Toyota Genuine ATF TYPE T-IV
22.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL
When disconnecting the cable, some systems need to be initialized after the cable is reconnected (See page General>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION).
23.INSPECT SHIFT LEVER POSITION
24.CHECK FOR EXHAUST GAS LEAKS
25.CHECK AUTOMATIC TRANSMISSION FLUID
26.INSTALL NO. 2 ENGINE UNDER COVER
27.INSTALL NO. 1 ENGINE UNDER COVER