Home › Engine / Hybrid System › HYBRID / BATTERY CONTROL › HV BATTERY › 2014.12–2017.06
RM2170E _51 Engine / Hybrid System _057004 HYBRID / BATTERY CONTROL _0277928 HV BATTERY A

HYBRID / BATTERY CONTROL  HV BATTERY  INSTALLATION  


PROCEDURE

Hide G92J5 1.INSTALL NO. 1 HYBRID BATTERY PACKING

CAUTION:

Be sure to wear insulated gloves and protective goggles.


a.

Connect the 2 wire harnesses to the No. 1 hybrid battery packing.


b.

Install the No. 1 hybrid battery packing with the 2 clamps.


Hide G920N 2.INSTALL UPPER HYBRID BATTERY COVER SUB-ASSEMBLY

CAUTION:

Be sure to wear insulated gloves and protective goggles.


a.

Install the upper hybrid battery cover sub-assembly with the 5 nuts.

Torque:
7.5 N*m (76 kgf*cm, 66 in.*lbf)


Hide G92E1 3.INSTALL NO. 1 HYBRID BATTERY COVER INTAKE DUCT

CAUTION:

Wear insulated gloves.


a.

Install the No. 1 hybrid battery cover intake duct with the clip.


b.

Install the HV battery thermistor to the No. 1 hybrid battery cover intake duct.


Hide G92Z0 4.INSTALL HYBRID BATTERY JUNCTION BLOCK ASSEMBLY

Hide G920R 5.INSTALL NO. 2 HYBRID BATTERY SHIELD SUB-ASSEMBLY

CAUTION:

Wear insulated gloves.


a.

Install the No. 2 hybrid battery shield sub-assembly with the 2 bolts and nut.

Torque:
7.5 N*m (76 kgf*cm, 66 in.*lbf)


Hide G920C 7.INSTALL NO. 2 HYBRID VEHICLE BATTERY CARRIER BRACKET SUB-ASSEMBLY

Hide G920Q 8.INSTALL NO. 1 HYBRID BATTERY SHIELD SUB-ASSEMBLY

Hide G9510 10.INSTALL HV BATTERY

CAUTION:

Wear insulated gloves.


NOTICE:

When removing/installing/moving the HV battery, make sure not to tilt it more than 80°.


a.

Install the HV battery with the 2 bolts and 2 nuts.

Torque:
19 N*m (194 kgf*cm, 14 ft.*lbf)


b.

Install the 2 clips.


Hide 12.CONNECT WIRE HARNESS

a.

Connect the 2 connectors and 3 clamps.


Hide G92N1A 14.INSTALL NO. 1 HYBRID VEHICLE BATTERY COVER PANEL LH

Hide G9230 15.INSTALL BATTERY COOLING BLOWER ASSEMBLY

NOTICE:
·

Be sure not to touch the fan part of the battery cooling blower assembly.

·

Do not lift the battery cooling blower assembly using its wire harness.



a.

Install the battery cooling blower assembly with the 2 bolts and nut.

Torque:
7.5 N*m (76 kgf*cm, 66 in.*lbf)


b.

Connect the battery cooling blower assembly connector and engage the clamp to the battery cooling blower assembly.


Hide G92F1 16.INSTALL NO. 1 HYBRID BATTERY EXHAUST DUCT

a.

Install the No. 1 hybrid battery exaust duct with the clip.


Hide 71033 17.INSTALL REAR SEAT CUSHION LEG SUB-ASSEMBLY

Hide 18.INSTALL REAR SEAT CUSHION ASSEMBLY (for Separate Type Seatback)

Hide 19.INSTALL REAR SEAT CUSHION ASSEMBLY (for Bench Type Seatback)