Home › Power Source / Network › POWER DISTRIBUTION › MAIN BODY ECU (for RHD)
RM3650E _57 Power Source / Network _079891 POWER DISTRIBUTION _0394793 MAIN BODY ECU(for RHD) A

POWER DISTRIBUTION  MAIN BODY ECU(for RHD)  INSTALLATION  


PROCEDURE

Hide 89221 1.INSTALL MAIN BODY ECU (MULTIPLEX NETWORK BODY ECU)

HINT:

Use the same procedure as for the LHD vehicles.

Click herePower Source / Network>POWER DISTRIBUTION>MAIN BODY ECU (for LHD)>INSTALLATION


Hide 62111C 2.INSTALL COWL SIDE TRIM BOARD RH

HINT:

Use the same procedure as for the LH side on the LHD vehicles.

Click hereVehicle Interior>INTERIOR PANELS / TRIM>INSTRUMENT PANEL SAFETY PAD>INSTALLATION


Hide 67913 3.INSTALL FRONT DOOR SCUFF PLATE RH

HINT:

Use the same procedure as for the LH side.

Click hereVehicle Interior>INTERIOR PANELS / TRIM>INSTRUMENT PANEL SAFETY PAD>INSTALLATION


Hide 58510H 4.INSTALL FLOOR MAT ASSEMBLY

Hide 73900 6.INSTALL LOWER NO. 1 INSTRUMENT PANEL AIRBAG ASSEMBLY

HINT:

Use the same procedure as for the LHD vehicles.

Click hereVehicle Interior>SUPPLEMENTAL RESTRAINT SYSTEMS>KNEE AIRBAG ASSEMBLY (for Driver Side)>INSTALLATION


Hide 55606 7.INSTALL NO. 1 INSTRUMENT PANEL UNDER COVER SUB-ASSEMBLY

Hide 78110K 8.INSTALL ACCELERATOR PEDAL(W/SENSOR) ROD ASSEMBLY

Hide 9.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

Hide 10. ENCODE/PROGRAM CONTROL UNIT(S)

NOTICE:
·

Use the most recent software version to prevent faults during programming/encoding.

·

The battery voltage must not drop below 13.0 V during programming.

·

Use only recommended chargers for a low-voltage vehicle electrical system.

·

Do not exceed the maximum charging voltage of 14.8 V when charging the battery.

·

When there is communication abnormality in the middle of work, control unit might be damaged.

·

It may be necessary to perform the Action Plan several times.



a.

Connect the battery charger to the vehicle.


b.

Connect the diagnosis system with the vehicle.


c.

Determine the action plan.

Service plan / Programming plan / Action plan / Calculate action plan


d.

Accept and fully process the measures plan.

Service plan / Programming plan / Action plan / Perform action plan


e.

Wait until programming/encoding has been completed.

NOTICE:

When there is communication abnormality in the middle of work, control unit might be damaged.



f.

Carry out vehicle test.

Vehicle management / Troubleshooting / Fault memory / Calculate test plan


g.

Delete the fault memory.

Vehicle management / Troubleshooting / Fault memory / Delete fault memory


h.

Disconnect the diagnosis system from the vehicle.


i.

Disconnect the battery charger from the vehicle.


Hide 11.PERFORM INITIALIZATION

a.

Connect the diagnosis system to the vehicle and enter the following menus:

Vehicle management / Service functions / Drive / Engine start / Reset starter lock / ABL Reset starter lock