Home › Engine / Hybrid System › 2GR-FE INTAKE / EXHAUST › INTAKE MANIFOLD
RM2030EQ _51 Engine / Hybrid System _014638 2GR-FE INTAKE / EXHAUST _0074433 INTAKE MANIFOLD A

2GR-FE INTAKE / EXHAUST  INTAKE MANIFOLD  INSTALLATION  


PROCEDURE

Hide 17111 1.INSTALL INTAKE MANIFOLD

a.

Set 2 new gaskets on each cylinder head sub-assembly.

NOTICE:
·

Align the port holes of the gaskets and cylinder head sub-assembly.

·

Make sure that the gaskets are installed in the correct direction.




b.

Set the intake manifold on the cylinder head sub-assembly.


c.

Install and tighten the 6 bolts and 4 nuts uniformly in several steps.

Torque:
21 N*m (214 kgf*cm, 15 ft.*lbf)


Hide 23807 2.INSTALL FUEL DELIVERY PIPE SUB-ASSEMBLY

Hide 23901 3.CONNECT FUEL TUBE SUB-ASSEMBLY

Hide 12327A 4.INSTALL NO. 2 ENGINE MOUNTING STAY RH (for Intake Manifold Side)

Hide 12327A 5.INSTALL NO. 2 ENGINE MOUNTING STAY RH (for Engine Mounting Stay Side)

Hide 17190 6.INSTALL INTAKE AIR SURGE TANK ASSEMBLY

NOTICE:

DO NOT apply oil to the bolts as listed below

Oil Application Prohibited Bolt
Intake Air Surge Tank Assembly and Intake Manifold
No. 1 Surge Tank Stay and Intake Air Surge Tank Assembly
Throttle Body Bracket and Intake Air Surge Tank Assembly


a.

Install 3 new gaskets to the intake air surge tank assembly.


b.

Temporarily install the intake air surge tank assembly with the 4 bolts and 2 nuts.


c.
A255341N01
1.313,1.719 1.49,1.906 0.177,0.188 10 true 1 0.469,1.292 0.646,1.479 0.177,0.188 10 true 5 1.906,1.76 2.063,1.927 0.156,0.167 10 true 4 2.646,1.385 2.802,1.563 0.156,0.177 10 true 6 1.833,0.844 2.01,1.031 0.177,0.188 10 true 3 1.229,0.781 1.427,0.948 0.198,0.167 10 true 2

Using a 5 mm hexagon socket wrench, in several steps, uniformly tighten the 4 bolts and 2 nuts in the order shown in the illustration.

Torque:
Bolt : 18 N*m (184 kgf*cm, 13 ft.*lbf)
Nut : 16 N*m (163 kgf*cm, 12 ft.*lbf)


d.

Install the throttle body bracket and No. 1 surge tank stay with the 2 bolts.

Torque:
21 N*m (214 kgf*cm, 15 ft.*lbf)


e.

Install the vacuum hose clamp with the bolt.

Torque:
5.4 N*m (55 kgf*cm, 48 in.*lbf)


f.

Connect the connector to the intake air control valve assembly.


g.

Connect the 2 water by-pass hoses and fuel vapor feed hose.


h.

Connect the connector and wire harness clamp to the throttle body assembly.


i.

Connect the check valve to brake booster hose (for RHD).


j.

Connect the hose clamp and union to check valve hose (for LHD).


k.

Connect the ventilation hose.


Hide 7.INSTALL AIR CLEANER CAP SUB-ASSEMBLY

Hide 55702A 8.INSTALL FRONT OUTER COWL TOP PANEL SUB-ASSEMBLY (for LHD)

Hide 55702A 9.INSTALL FRONT OUTER COWL TOP PANEL SUB-ASSEMBLY (for RHD)

Hide 10.INSTALL WINDSHIELD WIPER MOTOR AND LINK ASSEMBLY

Hide 11.CONNECT CABLE TO NEGATIVE BATTERY TERMINAL

NOTICE:

When disconnecting the cable, some systems need to be initialized after the cable is reconnected.

Click hereGeneral>INTRODUCTION>REPAIR INSTRUCTION>INITIALIZATION


Hide 11209 15.INSTALL V-BANK COVER SUB-ASSEMBLY